CCC Achieves Record-Breaking Milestone at Fadhili
A Testament to Innovation and Team Excellence
When ARAMCO challenged us to accelerate the Fadhili Gas Increment Program by five months, CCC didn’t just meet expectations—we redefined them.
Through bold innovation, including a shift to precast concrete construction, our team delivered the three-story GIS building ahead of schedule, completing 1,233 precast elements and 1,650 m³ of foundation concrete in just 10 months.
Other key buildings—MDS, SS-465, and PIB-365—are also on track to finish four months early, all while maintaining zero accidents during night operations.
This achievement reflects CCC’s core values: resilience, technical excellence, and collaboration.
We’re proud to set new benchmarks for industrial construction.