APLNG Pipelines, Queensland

EPC of 386km 42", 78km 36", 92km 30", 71.4km 24", and 39.5km 18" pipelines from the Surat basin to Gladstone to the APLNG's LNG process facility on Curtis Island.

Client

Australia Pacific LNG Pty Ltd. (APLNG) (an Origin Energy, ConocoPhillips & Sinopec JV)

Start / End

January 2010 / May 2014

QCLNG Export Pipeline - Narrows Crossing

EPC of a 12.9km 42" natural gas export pipeline, a 52km 42" pipeline parallel to mainline pipe, a delivery station, 2 x 1.3km HDD drives, a 1.5km cofferdam in marine clays, 2.4km of dredged trench and tow in dual pipelines across 2.5km open trench.

Client

QCLNG Pipeline Co. Ltd. (a British Gas Group Co.)

Start / End

September 2010 / November 2013

QCLNG Export Pipeline & Collection Header, Queensland

Detailed design and construction of a 334km 42" diameter natural gas export pipeline, a 193.9km 42" natural gas collection header, 6 connections from the CPPs to the collection Header (laterals) of 12 - 24" diameter pipelines, pigging facilities, and receipt station.

Client

QCLNG Pipeline Co. Ltd. (a British Gas Group Co.)

Start / End

July 2010 / February 2013

Papua New Guinea Cordinates
Close Papua New Guinea

Papua New Guinea Papua New Guinea Flag

  • P.1
  • P.2

PNG LNG Project - EPC Buildings, Utilities & Off-sites

EPC 27 no. buildings split into three main categories: Main Community Buildings, Non-Process Buildings, Process Buildings. Total built-up area of 31,800m2. Construction of utilities and off-site package including power generation, water system, air and nitrogren system BoG compressor, effluent/retention pond, module substations, flare system, and a 1.6km feed gas pipeline.

Client

Esso Highlands Ltd. (Onshore Works) & Esso Australia Pty Ltd. (Offshore Works)

Start / End

July 2010 / August 2013

PNG LNG Project, EPC5B Komo Airport and Infrastructure

Construction of a new airport with a 3,200 m runway, taxiways, arrival buildings, fuel storage facilities, radio and navigation equipment, and related infrastructures. Construction of a 21km heavy haul road, 2 new bridges, and associated drainage works.

The runway is considered the longest airfield in the Southern Hemisphere.

Client

Esso Highlands Ltd. (Onshore Works) & Esso Australia Pty Ltd. (Offshore Works)

Start / End

August 2009 / July 2012